Today i will be teaching us how to Estimate for soakaway pit. I know i have done something on this topic before now but i just want to give a more detailed estimate for students that may want to know how to do this and other professionals too!
So for this project, i will be giving estimates for a soakaway pit measuring 4268mm by 3048 (14 by 10 ft) and the estimate will provide for materials such as steel, cement, granite, wood (Boards and 3 by 4), blocks, binding wire, stirrups, sand, etc
![]() |
Figure 1 Showing the dimensions of a soakaway pit |
Uhh
From Figure 1 above, we have seen the dimensions of the soakaway pit to be designed. It is now time to start the estimation.
1. Excavation: You have to get 2 or 3 able bodied men on site to be able to completely excavate the pit and this could cost you N10,000 depending on your location.
Lets ask a very important question here
How many Blocks Do i need to construct a soakaway Pit?
For the septic tank under review, we have its length as 4268mm or 14 ft while the width is 3048mm or 10 ft and it also has a depth of 3048mm. Now lets estimate for the number of blocks required to carry out this project
From previous experience along with some basic mathematics, we have that the length of block is about 450mm
We also know that the height of a block is about 228mm and so we are going to try to get the number of blocks for every course as well as the number of blocks for each side of the pit
Lets not forget that the pit is 3048mm high and to get the number of coaches for soakaway pit, we have to divide the total height (3048mm) by the height of one block (228mm)
Thus, (3048/228) = 13.3 blocks high. Lets just assume its is 13 blocks high since we will be using Mortar for bonding
Having obtained the total number of courses as 13, let us estimate for the total number of blocks…
For Side A measuring 4268mm, we are going to divide this 4268 with the length of a block “450mm”
Thus, (4268/450) = 9.4 blocks
But we have 13 courses
Therefore, the total number of blocks for side A Would be 9.4 x 13 courses = 123 blocks
We are going to multiply this 123 blocks by 2 because we also have side “C-D”
123 X 2 = 246 Blocks
Next, we estimate for the number of blocks to over side “B-D”No
Dimension for sides B-D = 3048mm, we also understand the length of block is 450mm and there will be 13 courses
Therefore, let us divide 3048mm by 450mm
3048/450 = 6.7 blocks
6.7 x 13 courses = 87 blocks
We have 87 blocks for side B-D, So we multiply by 2 in order to provide for sides A-C since they both have the same dimensions
87 x 2 = 174
So the total number of blocks required for this septic tank project will be 174 + 246 = 420 blocks but we will add 42 for breakages
So the total number of blocks required would be 462 Blocks
How many Bags of cement would be required For a Soakaway Pit?
462/60 = 8 bags of cement (From experience, we need a bag of cement to lay 60 blocks)
How Much Binding wire is required for soakaway Septic tank Construction
For the Project under review, make available N1500 for Binding wire
How much Reinforcements for soakaway Septic tank
This totally depends on the size of the soakaway pit and the bar spacing
For this project, i chose 175mm spacing
4268/175 = 24 lengths of rod.
But the length of a reinforcement rod is 10,058mm and the span to be covered is 3048mm.
Therefore, we would need 10,058/3058 = 3.2 cuts from each length of rod
Now we have 24 slots along face A-B, So 24/3.2 = 8 Rods
Lets get the number of steel required for side B-D
we have 3048mm running to a length of 4268mm
so, 3048/175 = 17.4 lengths of rod
Where the length of rod = 10058mm, we have 10058/4268 = 2.3 cuts
so we have 17.4 slots for rods
But we can make 2.3 cuts from one length of rod
so 17.4/2.3 = 8 Lengths of reinforcement rods
Reinforcement for Columns or Pillars
So the height of the septic tank is 3048mm but the reinforcement would need additional 15mm
But a length of rod measures 10058mm and we are cutting 3063mm
it therefore means we can obtain 3 cuts from every length of rod.
We will need some 8 lengths of rod for the columns
In Total, we need 24 Lengths of 12mm rods for the job
Casting Of Top Slab
Top casting is 4268 x 3048 x 127 or 4.2 x 3 x 0.101 = 1.27m3 of concrete which means we are casting a cubic metre of concrete
So You need about 6 bags of cement for the top casting
A Trip of sand for all the work
A Trip of Granite if you didn’t have any on site before
Boards for top casting
16 pieces of 1 by 12 hard boards (2 will be used as inclined plane to send the blocks into the pit)
Nail
Provide 6 pound weight of nail
3 by 4 Wood for bracing
Provide 20 pieces
Bushwood or Bamboo for Support of formwork
Provide 30 lengths of bamboo ( a length is usually cut into 2)
Materials Needed for Building Septic Tank Soakaway
Blocks = 462
Rods = 24 lengths
Binding Wire = N1500
Cement For Block work = 8 Bags
Cement for top Casting = 6 bags
Cement for Bottom Casting = 6 Bags
Nail = 6 Pound weight
Boards for Top Casting= 16 pieces
3 by 4 wood = 20 pieces
Bushwood = 30 length
Total ========= N
Please i am not going to write anything as total amount, do your own market survey to find the total cost. However, the price of building materials in Nigeria is written here
Love what you read?
Notes: All of our services is at affordable prices, and we promise to render you good services.
OMORTUNDEY F.M.V. Business Productions Industrial Training is available for all people who are well wish to learn at our office
Click the link for Courses, Codes, and Units to fill in the form:
Click the links for FORM
Note: Anybody Trained under us have discount and has access to be employed direct.
ALWAYS CHECK FOR MORE UPDATES. . .
ALWAYS CHECK FOR MORE UPDATES. . .
WHAT DO YOU THINK? - We have all sinned and deserve God's judgment. God, the Father, sent His only Son to satisfy that judgment for those who believe in Him. Jesus, the creator and eternal Son of God, who lived a sinless life, loves us so much that He died for our sins, taking the punishment that we deserve, was buried, and rose from the dead according to the Bible. If you truly believe and trust this in your heart, receiving Jesus alone as your Savior, declaring, "Jesus is Lord," you will be saved from judgement, and spend eternity with God in heaven.
What is your response?Yes, today, I'm deciding to follow Jesus
Yes, I'm already the follower of Jesus.
GET BUY YOUR BIBLE, Books, Dictionary, and Others for yourself, your, children, and family @OMORTUNDEY FREELANCE MULTI-LEVEL VENTURES LIBRARY on visiting or with delivery to your location.
If you would like to SPONSOR or DONATE to OMORTUNDEY Freelance Multi-Level Ventures, please CLICK HERE.
What is your response?
Yes, today, I'm deciding to follow JesusGET BUY YOUR BIBLE, Books, Dictionary, and Others for yourself, your, children, and family @OMORTUNDEY FREELANCE MULTI-LEVEL VENTURES LIBRARY on visiting or with delivery to your location.
If you would like to SPONSOR or DONATE to OMORTUNDEY Freelance Multi-Level Ventures, please CLICK HERE.
To meet your needs with O.F.M.V click on: http://metyourneeds.blogspot.com/
[Home Page] [Met your needs] [About OMORTUNDEY Freelance Multi-Level Ventures] [OMPHI City] [Company Overview] [Our Objectives] [Our Vision] [Our Goals] [Our Products and Services] [Our Blog] [Networking & Communications] [Consultancy] [Sales of Products Suppliers] [Industrial Training (I.T)] [Payment Rules and Regulations] [Sponsors or Fund Raising] [OMORTUNDEY F.M.V. Proposals for Partnerships] [OMORTUNDEY F.M.V. Banks & Accounts] [Social Media] [Our Address] [Our Contacts] [Carrier and Opportunity] [Notice for all our Clients]
Goto our Sections Business sites: [Footwear & Leather Production] [Computer & Businesses][Films & Theatre Studios] [Home Planning & Building Engineer] [Farm Food Production] [Fashion, Wears & Printing Production] [Home-made & Cosmetics Production] [Iron & Metal Works production] [Aluminium & Glass production] [Furniture & Upholstery] [Health Care] [Post Office Box] [Books & Publishing] [Import & Export of Goods] [Accomodations & Properties] [Vegetable Oil Dealer] [Multi-Links] [Ice-Block Depot, Drinks, Provision & Business Ventures] [Downloading Software] [Music & Downloading] [Video & Downloading] [GFM Holy-Bible Reading Online] [School and Education Study Online] [Dictionary Online] [GOto World-Blog] [GOto WebChatrooms] [GOto Word of Wisdom] [GOto Answers.com]
To meet your needs with O.F.M.V click on: http://metyourneeds.blogspot.com/
[Home Page] [Met your needs] [About OMORTUNDEY Freelance Multi-Level Ventures] [OMPHI City] [Company Overview] [Our Objectives] [Our Vision] [Our Goals] [Our Products and Services] [Our Blog] [Networking & Communications] [Consultancy] [Sales of Products Suppliers] [Industrial Training (I.T)] [Payment Rules and Regulations] [Sponsors or Fund Raising] [OMORTUNDEY F.M.V. Proposals for Partnerships] [OMORTUNDEY F.M.V. Banks & Accounts] [Social Media] [Our Address] [Our Contacts] [Carrier and Opportunity] [Notice for all our Clients]
Goto our Sections Business sites:
[Footwear & Leather Production] [Computer & Businesses][Films & Theatre Studios] [Home Planning & Building Engineer] [Farm Food Production] [Fashion, Wears & Printing Production] [Home-made & Cosmetics Production] [Iron & Metal Works production] [Aluminium & Glass production] [Furniture & Upholstery] [Health Care] [Post Office Box] [Books & Publishing] [Import & Export of Goods] [Accomodations & Properties] [Vegetable Oil Dealer] [Multi-Links] [Ice-Block Depot, Drinks, Provision & Business Ventures] [Downloading Software] [Music & Downloading] [Video & Downloading] [GFM Holy-Bible Reading Online] [School and Education Study Online] [Dictionary Online] [GOto World-Blog] [GOto WebChatrooms] [GOto Word of Wisdom] [GOto Answers.com]
ONE HOLD, ONCE UNITED, ONE WORLD...
TOGETHER, WE RISE TO THE FUTURE.
No comments:
Post a Comment